Projected project cost
-$1.9 million
Proposed Schedule:
Repair existing bridge
- 47 Pics -
COMPLETED
Kiosk Removal
- 20 Pics -
COMPLETED
Stormdrain & Footings Construction,
Curbs, Driveways and Sidewalks west side
- 682 Pics -
COMPLETED
Construction of New Bridge
- 828 Pics -
COMPLETED
Remove Old Bridge
- 442 Pics -
COMPLETED
IN PROGRESS
-
New Curbs and Sidewalks East Side, Landscaping
For more complete information
contact Public Works Director Aaron Geisler at 623-9287
Pictures will be taken as work on the bridge progresses
Check back often for updates.